Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Install topping slabs

Install topping slabs

Unit of competency
National Code
CPCCCO3055A
State Code
WI740
TGA Status
Replaced
DTWD Status
Replaced
Current Release Number
1.00
Current Release Date
17/01/2014
State Implementation and Classification
Approved Date
20/06/2014
Field of Education
040399 - Building, N.e.c.
Original Release Date
20/06/2014
Nominal Hours
16
Description
This unit of competency specifies the outcomes required to install bonded or unbonded topping slabs to existing concrete.The unit includes grinding and scabbling preparation techniques. It may also include working with others and as a member of a team.
Notes
Elements and Performance Criteria
1 Plan and prepare.
  • 1.1 Work instructions, work health and safety (WHS) requirements and other information relevant to the work are identified, confirmed and applied for planning and preparation purposes.
  • 1.2 Plant, tools and equipment consistent with job requirements are selected and checked for serviceability, and faults are rectified and reported before work begins.
  • 1.3 Material quantity requirements are identified and calculated according to plans, specifications and quality requirements.
  • 1.4 Materials appropriate to the work application are obtained, prepared, safely handled and located ready for use.
  • 1.5 Environmental requirements are identified for the project according to environmental plans and regulatory obligations.
2 Prepare concrete for topping slab.
  • 2.1 Need for concrete reinforcement is determined through consultation with relevant personnel and reinforcement is installed as required according to specifications.
  • 2.2 Preparation equipment is selected for the process.
  • 2.3 Existing concrete is scarified using appropriate preparation techniques according to specifications.
  • 2.4 Surface area to be topped is cleared of loose particles and debris.
  • 2.5 Existing control joints in substrate are checked to ensure they are carried through and reflected in the proposed topping.
3 Pour concrete slab.
  • 3.1 Existing concrete surface is prepared for topping slab with bonded topping or separation material according to specifications.
  • 3.2 Topping slab is poured on to existing concrete surface and screeded to specifications.
4 Cure and seal concrete.
  • 4.1 Following setting, curing agents and curing techniques are applied to concrete according to specifications.
  • 4.2 Curing and sealing are maintained for period specified according to specifications.
5 Clean up.
  • 5.1 Work area is cleared and materials disposed of, reused or recycled according to regulations, codes of practice and job specification.
  • 5.2 Plant, tools and equipment are cleaned, checked, maintained and stored according to manufacturer recommendations and standard work practices.
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Work health and safety requirements must comply with state and territory legislation and regulations and project safety plan, and may include:
assistance of others or the use of manual or mechanical lifting devices with handling activities where size, weight or other issues, such as disability, are a factor
emergency procedures, including extinguishing fires, organisational first aid requirements, and evacuation procedures
hazard control
hazardous materials and substances
personal protective equipment (PPE) prescribed under legislation, regulations and workplace policies and practices
safe operating procedures, including the conduct of operational risk assessment and treatments associated with:
earth leakage boxes
lighting
power cables, including overhead service trays, cables and conduits
restricted access barriers
surrounding structures
traffic control
trip hazards
work site visitors and the public
working at heights
working in confined spaces
working in proximity to others
working outdoors in warm climates
use of firefighting equipment
use of tools and equipment
workplace environmental requirements and safety.
Information may include:
instructions issued by authorised organisational and external personnel
memos
regulatory and legislative requirements relating to resurfacing concrete
relevant Australian standards
safe work procedures relating to resurfacing concrete
safety data sheets
signage
verbal, written and diagrammatic instructions, including manufacturer specifications and instructions where specified
work bulletins
work schedules, plans and specifications.
Planning and preparation must include:
assessing conditions and hazards
determining work requirements and safety plans and policies
identifying and rectifying equipment defects
inspecting work sites.
Tools and equipment:
must include:
brooms
floats
hoses
scabblers
screeds
shovels
trowels
wheelbarrows
may include:
concrete mixers
grinders
power trowels
rollers
sand and water blasters.
Quality requirements must include:
internal organisational quality policy and standards
manufacturer specifications where specified
relevant regulations and Australian standards
workplace operations and procedures.
Materials:
must include concrete
may include:
acid solutions for cleaning and etching
bonding agents
curing compounds.
Environmental requirements may include:
clean-up management
dust and noise control
stormwater management
vibration management
waste management.
Relevant personnel may include:
engineer
site manager.
Preparation techniques may include:
abrasive blasting (sand or grit)
acid etching
grinding
scabbling.
Curing agents may include:
water-based curing compounds
hessian
polythene sheets
water.
Curing techniques may include:
applying curing agents
applying plastic film
hosing
ponding
using sprinklers.
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment
This unit of competency could be assessed by undertaking a range of tasks in the workplace or a close simulation of the workplace environment, provided that simulated or project-based assessment techniques fully replicate construction workplace conditions, materials, activities, responsibilities and procedures.
Critical aspects for assessment and evidence required to demonstrate competency in this unit
A person should demonstrate the ability to:
prepare the surfaces of at least four existing concrete slabs each measuring at least 10 square metres; two slabs must be prepared for bonded topping slabs and two for unbonded topping slabs
install bonded and unbonded topping slabs to prepared surfaces
cure and finish the topping slabs to specifications
locate, interpret and apply relevant information, standards and specifications relating to installing topping slabs
comply with site safety plans and procedures
comply with organisational policies and procedures relating to installing topping slabs while maintaining quality requirements outlined in job requirements
safely and effectively operate and use plant, tools and equipment required to install topping slabs
communicate and work effectively and safely with others.
Context of and specific resources for assessment
Assessment of this unit:
must be in the context of the work environment
may be conducted in an off-site context, provided it is realistic and sufficiently rigorous to cover all aspects of workplace performance, including task skills, task management skills, contingency management skills and job role environment skills
must meet relevant compliance requirements.
Resource implications for assessment include:
an induction procedure
realistic tasks or simulated tasks covering the mandatory task requirements
relevant specifications and work instructions
tools and equipment appropriate to applying safe work practices
support materials appropriate to activity
workplace instructions relating to safe work practices and addressing hazards and emergencies
safety data sheets.
Method of assessment
Assessment for this unit must verify the practical application of the required skills and knowledge, using a combination of the following methods:
direct observation of tasks in real or simulated work conditions
questioning to confirm the ability to consistently identify and correctly interpret the essential underpinning knowledge required for practical application
review of relevant authenticated documentation from third parties, such as existing supervisors, team leaders or specialist training staff.
Guidance information for assessment
This unit could be assessed on its own or in combination with other units relevant to the job function.
Reasonable adjustments for people with disabilities must be made to assessment processes where required. This could include access to modified equipment and other physical resources, and the provision of appropriate assessment support.
Assessment processes and techniques should, as far as is practical, take into account the language, literacy and numeracy capacity of the candidate in relation to the competency being assessed.
Replaces
State Code National Code Title Type
D7363 CPCCCO3025A Resurface concrete Unit of competency
Replaced By
State Code National Code Title Type
OAP39 CPCCCO3055 Install topping slabs Unit of competency
State Code National Code Title Type
J784 CPC30313 Certificate III in Concreting Qualification