Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Manage project time
Manage project time
Unit of competency
National Code
BSBPMG512A
BSBPMG512A
State Code
WG099
WG099
TGA Status
Replaced
Replaced
DTWD Status
Replaced
Replaced
State Implementation and Classification
Approved Date
30/05/2014
Field of Education
080315 - Project Management
Original Release Date
30/05/2014
Nominal Hours
40
Description
This unit describes the performance outcomes, skills and knowledge required to manage time in projects. It involves determining and implementing the project schedule, and assessing time-management outcomes.
Notes
Elements and Performance Criteria
1. Determine project schedule
- 1.1 Develop the work breakdown structure with sufficient detail to enable effective planning and control
- 1.2 Estimate the duration and effort, sequence and dependencies of tasks to achieve project deliverables
- 1.3 Use project-scheduling tools and techniques to identify schedule impact on project time management, resource requirements, costs and risks
- 1.4 Contribute to achieving an agreed schedule baseline and communication of the schedule to stakeholders
2. Implement project schedule
- 2.1 Implement mechanisms to measure, record and report progress of activities in relation to the agreed schedule
- 2.2 Conduct ongoing analysis to identify baseline variance
- 2.3. Analyse and forecast the impact of changes to the schedule
- 2.4 Review progress throughout the project life cycle and implement agreed schedule changes
- 2.5 Develop responses to potential or actual schedule changes and implement them to maintain project objectives
3. Assess time-management outcomes
- 3.1 Review schedule performance records to determine the effectiveness of time-management activities
- 3.2 Identify and document time-management issues and recommend improvements
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Work breakdown structure may include:
activity and task descriptors
high-level deliverables framework
multi-level task granulation
work breakdown task dictionary.
Estimating the duration and effort may include:
allowance for contingency and risk
availability of resources and supplies
degree of variation
expert opinion
level of accuracy
prior project history
regulations and standards governing resource performance
top-down or bottom-up estimating.
Sequence and dependencies may include:
deliverable milestones
preferred, logical or required order of task completion
relationship between tasks impacting on start and finish times and dates.
Project-scheduling tools and techniques may include:
bar charts
conducting or supervising qualitative and/or quantitative time analysis, such as schedule simulation, decision analysis, contingency planning and 'what if' scenarios
critical chain management
critical path diagrams
Gantt charts
project schedule network diagrams
standalone, organisation-integrated or cloud-based software tools
using personal experience and/or subject matter experts
using specialist time-analysis tools to assist in the decision-making process.
Schedule impact may include:
accuracy of estimates
advances or delays in task completion
changes to project risk
changes to resources and cost
degree of change to baseline
relevance of task dependencies.
Schedule baseline may include:
assigned responsibility
assigned schedule-management responsibilities
charted milestones
contingency plans
project schedule and sub-schedules
critical path analysis
resource assignment to task
schedule-management strategies and actions.
Agreed schedule changes may include:
applied constraints
changing objectives
changing scope
delayed or advanced task completion
resource availability.
Review of schedule performance may occur at:
agreed major milestones, e.g. phases and subcontracts
change of key personnel
completion of major deliverables
finalisation of project and other agreed milestones.
Records may include:
diaries, incident logs, occurrence reports and other such records
evaluation of options
Gantt, PERT and other scheduling charts
lists of variances and forecasts of potential scheduled events
project and/or organisation files and records
recommended and approved courses of action
records of analysis
work breakdown structure.
Work breakdown structure may include:
activity and task descriptors
high-level deliverables framework
multi-level task granulation
work breakdown task dictionary.
Estimating the duration and effort may include:
allowance for contingency and risk
availability of resources and supplies
degree of variation
expert opinion
level of accuracy
prior project history
regulations and standards governing resource performance
top-down or bottom-up estimating.
Sequence and dependencies may include:
deliverable milestones
preferred, logical or required order of task completion
relationship between tasks impacting on start and finish times and dates.
Project-scheduling tools and techniques may include:
bar charts
conducting or supervising qualitative and/or quantitative time analysis, such as schedule simulation, decision analysis, contingency planning and 'what if' scenarios
critical chain management
critical path diagrams
Gantt charts
project schedule network diagrams
standalone, organisation-integrated or cloud-based software tools
using personal experience and/or subject matter experts
using specialist time-analysis tools to assist in the decision-making process.
Schedule impact may include:
accuracy of estimates
advances or delays in task completion
changes to project risk
changes to resources and cost
degree of change to baseline
relevance of task dependencies.
Schedule baseline may include:
assigned responsibility
assigned schedule-management responsibilities
charted milestones
contingency plans
project schedule and sub-schedules
critical path analysis
resource assignment to task
schedule-management strategies and actions.
Agreed schedule changes may include:
applied constraints
changing objectives
changing scope
delayed or advanced task completion
resource availability.
Review of schedule performance may occur at:
agreed major milestones, e.g. phases and subcontracts
change of key personnel
completion of major deliverables
finalisation of project and other agreed milestones.
Records may include:
diaries, incident logs, occurrence reports and other such records
evaluation of options
Gantt, PERT and other scheduling charts
lists of variances and forecasts of potential scheduled events
project and/or organisation files and records
recommended and approved courses of action
records of analysis
work breakdown structure.
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment
Critical aspects for assessment and evidence required to demonstrate competency in this unit
Evidence of the following is essential:
demonstrated successful application of time-management tools and techniques for a project of sufficient complexity to demonstrate the full range of performance requirements
knowledge of time-management methodologies, and their capabilities, limitations, application and outcomes.
Context of and specific resources for assessment
Assessment must ensure:
access to workplace documentation, schedules and reports from project team
consideration of feedback from project stakeholders regarding the management of project time.
Method of assessment
A range of assessment methods should be used to assess practical skill and knowledge. The following examples are appropriate for this unit:
direct questioning combined with review of portfolios of evidence and third-party workplace reports of on-the-job performance by the candidate
oral or written questioning to assess knowledge of strategies for managing project time and their application in different situations
analysis of responses in addressing case studies and scenarios that present project time-management issues and problems
review of progress throughout project life cycle; and review of implementation of agreed schedule changes
assessment of documented time-management issues and recommended improvements.
Guidance information for assessment
Holistic assessment with other units relevant to the industry sector, workplace and job role is recommended.
Overview of assessment
Critical aspects for assessment and evidence required to demonstrate competency in this unit
Evidence of the following is essential:
demonstrated successful application of time-management tools and techniques for a project of sufficient complexity to demonstrate the full range of performance requirements
knowledge of time-management methodologies, and their capabilities, limitations, application and outcomes.
Context of and specific resources for assessment
Assessment must ensure:
access to workplace documentation, schedules and reports from project team
consideration of feedback from project stakeholders regarding the management of project time.
Method of assessment
A range of assessment methods should be used to assess practical skill and knowledge. The following examples are appropriate for this unit:
direct questioning combined with review of portfolios of evidence and third-party workplace reports of on-the-job performance by the candidate
oral or written questioning to assess knowledge of strategies for managing project time and their application in different situations
analysis of responses in addressing case studies and scenarios that present project time-management issues and problems
review of progress throughout project life cycle; and review of implementation of agreed schedule changes
assessment of documented time-management issues and recommended improvements.
Guidance information for assessment
Holistic assessment with other units relevant to the industry sector, workplace and job role is recommended.
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| D0931 | BSBPMG503A | Manage project time | Unit of competency |
Replaced By
| State Code | National Code | Title | Type |
|---|---|---|---|
| AUM39 | BSBPMG512 | Manage project time | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| J666 | RII50513 | Diploma of Civil Construction Design | Qualification |
| J681 | RII50413 | Diploma of Civil Construction Management | Qualification |
| D170 | BSB50807 | Diploma of International Business | Qualification |
| J521 | BSB51413 | Diploma of Project Management | Qualification |