Unit of competency Outline
Date retreived
23/07/2026 7:07 AM AWST
23/07/2026 7:07 AM AWST
Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Conduct site survey for off-grid photovoltaic/generating set systems
Conduct site survey for off-grid photovoltaic/generating set systems
Unit of competency
National Code
UEERE0055
UEERE0055
State Code
OEU38
OEU38
TGA Status
Current
Current
DTWD Status
Approved
Approved
State Implementation and Classification
Approved Date
16/03/2023
Field of Education
031399 - Electrical And Electronic Engineering And Technology, N.e.c.
Original Release Date
16/03/2023
Nominal Hours
36
Description
This unit involves the skills and knowledge required to complete site surveys for off-grid photovoltaic/generating set systems.It includes safe work practices, site survey processes and procedures, service provider responsibilities, consulting with qualified people to assess client energy demand requirements and assessing off-grid equipment options to meet client requirements and site conditions. It also covers provision of advice to the client on energy storage standards, codes of practices, government/utilities incentive schemes, and information related to the installation of off-grid renewable energy (RE) generation systems.No licensing, legislative or certification requirements apply to this unit at the time of publication.
Notes
Elements and Performance Criteria
1 Prepare to conduct site survey
- 1.1 Stakeholders are identified and client requirements and expectations for off-grid system obtained
- 1.2 Work health and safety (WHS)/occupational health and safety (OHS) requirements, relevant legislated requirements, and workplace procedures relevant to site survey are obtained and applied
- 1.3 Equipment and documentation needed for the site inspection are obtained in accordance with workplace procedures
- 1.4 Requirements for site survey and roles/responsibilities of people involved in site survey, design and installation are discussed with client
- 1.5 General information about industry standards, building/electrical regulations and codes, and risk minimisation is provided to client
- 1.6 Advice on the benefits of renewable energy generation systems and energy management is provided to client
- 1.7 Current client energy usage data is collected, and future changes identified
- 1.8 Resources, information sources and other people that will support gathering required site survey information are identified
2 Undertake and document site survey
- 2.1 Site survey for the proposed installation is safely undertaken
- 2.2 Current and expected future client energy generation needs are discussed, and expectations are clarified
- 2.3 Potential locations of equipment are discussed with client and preferences recorded
- 2.4 Site hazards that may impact installation are identified and documented
- 2.5 Information about site access, building structures, existing electrical infrastructure including existing RE and generation elements, available RE resources is gathered and included in report
- 2.6 Site survey report is prepared and provided to designer in accordance with workplace procedures
- 2.7 Designer, and other qualified person/s if required, are consulted and briefed on client expectations and requirements
- 2.8 Designer, and other qualified person/s if required, are consulted and briefed on site access, conditions, risks and potential installation issues
- 2.9 Options for off-grid energy generation and storage equipment to meet site requirements and client expectations are discussed with designer, and other qualified person/s if required
- 2.10 Placement of system components is considered, and any restrictions or issues of concern noted
- 2.11 Final site survey report is prepared after consultation with designer