Unit of competency Outline

Date retreived
23/07/2026 1:09 PM AWST

Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Install LPG storage of aggregate storage capacity exceeding 500 litres and less than 8 kl

Install LPG storage of aggregate storage capacity exceeding 500 litres and less than 8 kl

Unit of competency
National Code
CPCPGS3060
State Code
OCN18
TGA Status
Current
DTWD Status
Approved
Current Release Number
2.00
Current Release Date
23/12/2020
State Implementation and Classification
Approved Date
01/06/2021
Field of Education
040327 - Plumbing
Original Release Date
01/06/2021
Nominal Hours
8
Description
This unit specifies the skills and knowledge required to select, locate and install liquefied petroleum gas (LPG) storage of 500 to 8000 litres aggregate capacity.In some jurisdictions, this unit of competency may form part of accreditation, licensing, legislative, regulatory or certification requirements.
Notes
Elements and Performance Criteria
1 Plan the work.
  • 1.1 Access, read and determine LPG system installation requirements from relevant job plans and specifications, codes, Australian standards, manufacturer’s specifications and jurisdictional requirements.
  • 1.2 Identify and apply workplace policies and procedure and work health and safety (WHS) and environmental requirements.
  • 1.3 Determine gas load and design requirements.
  • 1.4 Check storage capacity for compliance with relevant job plans and specifications, codes, Australian standards, manufacturer’s specifications and jurisdictional requirements.
  • 1.5 Determine appropriate regulators to meet capacity and load of the system.
  • 1.6 Select the location of LPG cylinders or tank according to relevant job plans and specifications, codes, relevant Australian standards, manufacturer’s specifications and jurisdictional requirements.
2 Prepare for work.
  • 2.1 Create a materials list and collect materials.
  • 2.2 Select appropriate tools and equipment, including personal protective equipment (PPE).
  • 2.3 Select appropriate testing equipment.
  • 2.4 Prepare work area and materials to support installation.
3 Install and test LPG storage system.
  • 3.1 Install LPG storage container/s, piping, fittings and components in compliance with relevant job plans and specifications, codes, Australian standards, manufacturer’s specifications and jurisdictional requirements.
  • 3.2 Install regulators and associated pipework, in compliance with relevant job plans and specifications, codes, Australian standards, manufacturer’s specifications and jurisdictional requirements.
  • 3.3 Test and purge installation.
  • 3.4 Commission installation, including checking regulator working and lockup pressure.
  • 3.5 Complete documentation according to installation requirements and/or workplace procedures.
4 Clean up.
  • 4.1 Clear the work area, and dispose of, reuse or recycle materials in accordance with state and territory legislation and workplace policies and procedures.
  • 4.2 Clean tools and equipment, check for serviceability and report any damage, and store and secure.
No information
No information
State Code National Code Title Type
BGB7 CPC32720 Certificate III in Gas Fitting Qualification