Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Plan on-site irrigation system installation and construction work

Plan on-site irrigation system installation and construction work

Unit of competency
National Code
AHCIRG406A
State Code
D6884
TGA Status
Deleted
DTWD Status
Deleted
Current Release Number
1.00
Current Release Date
10/06/2011
State Implementation and Classification
Approved Date
14/11/2012
Field of Education
080315 - Project Management
Original Release Date
14/11/2012
Nominal Hours
30
Description
This unit covers planning on-site irrigation system installations and construction work and defines the standard required to: identify operational requirements from contract documentation; develop strategies and plan procedures for installation and construction; develop a project plan with tasks, responsibilities, timelines and costs.
Notes
Elements and Performance Criteria
1. Appraise contract documentation and translate into operational requirements
  • 1.1. Copy of building approval and conditions is obtained as required.
  • 1.2. Contract documentation is reviewed for any unusual aspects of construction, use of materials and penalties.
  • 1.3. Availability of sub-contractors is ascertained and selected to suit job requirements.
  • 1.4. Availability of materials is checked with suppliers.
  • 1.5. Site access limitations are assessed.
  • 1.6. Relevant authorities controlling construction work advised of commencement date for project as required.
2. Develop strategies for implementing the construction operations
  • 2.1. Procedures for controlling and recording site deliveries are established.
  • 2.2. Procedures for recording the hire of plant and equipment are determined.
  • 2.3. Occupational Health and Safety (OHS) procedures are established, including hazard/risk management.
  • 2.4. Procedures are established for dealing with environmental issues associated with irrigation construction work.
  • 2.5. Procedures required for the control of multiple projects are determined.
3. Prepare project schedule for irrigation installation and construction
  • 3.1. Construction operations are prepared in sequence.
  • 3.2. Operations are entered into a manually prepared schedule or computer based software package.
  • 3.3. 'Critical path' is identified and schedule revised with new activities/projects, as needed, and documented.
  • 3.4. Timeframe is adjusted to take account of anticipated delays.
4. Determine all the required resources for project
  • 4.1. Temporary services and site accommodation is determined as required.
  • 4.2. Plant requirements and dates are selected and accessed.
  • 4.3. On site labour requirements are determined.
5. Prepare dilapidation report
  • 5.1. Records are made of the condition of existing building(s) to be retained and structures on the adjacent site boundaries.
  • 5.2. Copies of reports are submitted to adjacent building owners prior to commencing construction.
RANGE STATEMENT
The range statement relates to the unit of competency as a whole.
Planning may include:
the planning of installation and construction work for both gravity fed and pressurised irrigation systems.
EVIDENCE GUIDE
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment

Critical aspects for assessment and evidence required to demonstrate competency in this unit
The evidence required to demonstrate competency in this unit must be relevant to workplace operations and satisfy holistically all of the requirements of the performance criteria and required skills and knowledge and include achievement of the following:
identify operational requirements from contract documentation
develop strategies and plan procedures for installation and construction
develop a project plan with tasks, responsibilities, timelines and costs.
Context of and specific resources for assessment
Competency requires the application of work practices under work conditions. Selection and use of resources for some worksites may differ due to the regional or enterprise circumstances.
Replaces
State Code National Code Title Type
S3604 RTE4607A Plan on-site irrigation system installation and construction work Unit of competency