Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Plan layout of a residential sanitary plumbing system

Plan layout of a residential sanitary plumbing system

Unit of competency
National Code
CPCPSN3011A
State Code
D7491
TGA Status
Replaced
DTWD Status
Replaced
Current Release Number
1.00
Current Release Date
19/05/2011
State Implementation and Classification
Approved Date
11/10/2011
Field of Education
040327 - Plumbing
Original Release Date
11/10/2011
Nominal Hours
16
Description
This unit of competency specifies the outcomes required to plan the layout, size and install a sanitary plumbing system for residential buildings.
Notes
Elements and Performance Criteria
1. Prepare for work.
  • 1.1. Information, plans and specifications are obtained for planned work activity.
  • 1.2. Safety (OHS) requirements associated with planning the layout of sanitary plumbing systems, and workplace environmental requirements, are adhered to throughout the work.
  • 1.3. Quality assurance requirements are identified and adhered to in accordance with workplace requirements.
  • 1.4. Tasks are planned and sequenced in conjunction with others involved in or affected by the work and statutory and regulatory authority requirements.
  • 1.5. Tools and equipment for planning the layout of sanitary plumbing systems, including personal protective equipment, are selected and checked for serviceability.
  • 1.6. Work area is prepared to support efficient planning of the layout of sanitary plumbing systems.
2. Plan system layout.
  • 2.1. Site inspection is undertaken to determine job requirements.
  • 2.2. Quantity, location and type of fixtures are determined from design drawings, plans and elevations and other relevant information.
  • 2.3. Layout of sanitary plumbing system is planned in accordance with plans and relevant Australian standards.
  • 2.4. Materials and fixtures required are determined from proposed design.
  • 2.5. Sustainability principles and concepts are applied to work preparation and application.
  • 2.6. Plans are recorded in accordance with workplace requirements.
3. Clean up.
  • 3.1. Work area is cleared and materials disposed of, reused or recycled according to legislation, regulations, codes of practice and job specification..
  • 3.2. Tools and equipment are cleaned, checked, maintained and stored in accordance with manufacturer recommendations and workplace procedures.
  • 3.3. Documentation is completed in accordance with workplace requirements.
No information
No information
Replaces
State Code National Code Title Type
W9751 CPCPSN3001A Plan layout of a residential sanitary plumbing system Unit of competency
Replaced By
State Code National Code Title Type
WF957 CPCPSN3011B Plan layout of a residential sanitary plumbing system Unit of competency
State Code National Code Title Type
D411 CPC32411 Certificate III in Plumbing Qualification