Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Plan a Scheduled Outage
Plan a Scheduled Outage
Unit of competency
National Code
UEPOPS423A
UEPOPS423A
State Code
S5265
S5265
TGA Status
Replaced
Replaced
DTWD Status
Replaced
Replaced
State Implementation and Classification
Approved Date
31/05/2011
Field of Education
031313 - Electrical Fitting, Electrical Mechanics
Original Release Date
31/05/2011
Nominal Hours
60
Description
1)
This unit deals with the skills and knowledge required to plan for a scheduled outage.
This unit deals with the skills and knowledge required to plan for a scheduled outage.
Notes
Elements and Performance Criteria
1 Identify outage requirements
- 1.1 Outage requirements are identified from notification of requirement, work orders or equivalent and clarified with the appropriate parties and/or site inspection
- 1.2 Safety issues are identified to comply with statutory enterprise and site requirements
- 1.3 Date, time and expected duration of outage is assessed and confirmed
- 1.4 Schematic diagrams, drawings, plans and/or maps are consulted to determine area affected
- 1.5 Where appropriate, the teams and individuals roles and responsibilities within the team are identified and, where required, assist in the provision of the on-the-job training.
2 Create outage plan
- 2.1 Statistical records are consulted to ascertain most favourable time for outage
- 2.2 Implications of outage are identified and assessed to ascertain impact of outage
- 2.3 Identify key stakeholders and/or equipment affected
- 2.4 Current status of affected equipment and consumers is identified and assessed
- 2.5 Consult with all key stakeholders to determine whether contingency plans require implementation and/or timetables require review is carried out in accordance with enterprise policy
- 2.6 Disruptions to key consumers are minimised by providing alternative routes of supply
- 2.7 Scope of work to be carried out during outage is evaluated against the allocated time frame.
- 2.8 Types of permits required to undergo work prior to and during outage are established in accordance with enterprise procedures
- 2.9 Notification of requirement or other pre-emptive request is approved in accordance with enterprise procedures
3 Implement outage plan
- 3.1 Work crews are notified of the outage plan through the appropriate channels in accordance with enterprise procedures
- 3.2 Notification of outage is communicated to all stakeholders in accordance with enterprise procedures
4 Complete documentation
- 4.1 Documentation is updated, files and records maintained in accordance with enterprise/site procedures.
No information
No information
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| AYG10 | UTPNEG274A | Plan a scheduled outage | Unit of competency |
Replaced By
| State Code | National Code | Title | Type |
|---|---|---|---|
| WE406 | UEPOPS423B | Plan a scheduled outage | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| S503 | UEP40106 | Certificate IV in ESI Generation (Systems Operations) | Qualification |