Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Install fixed fire pumpsets
Install fixed fire pumpsets
Unit of competency
National Code
CPCPFS3048
CPCPFS3048
State Code
OCO16
OCO16
TGA Status
Current
Current
DTWD Status
Approved
Approved
State Implementation and Classification
Approved Date
01/06/2021
Field of Education
039905 - Fire Technology
Original Release Date
01/06/2021
Nominal Hours
24
Description
This unit of competency specifies the skills and knowledge required to install fixed fire pumpsets, including the pump base, power sources, pumps, pipework and associated components in new or existing, domestic or commercial structures.In some jurisdictions, this unit of competency may form part of accreditation, licensing, legislative, regulatory or certification requirements.
Notes
Elements and Performance Criteria
1 Plan the work.
- 1.1 Access, read and apply fixed fire pumpsets installation requirements relevant job plans and specifications, codes, Australian Standards, manufacturer’s specifications and jurisdictional requirements.
- 1.2 Identify and apply workplace policies and procedures, work health and safety (WHS) and environmental requirements.
2 Prepare for work.
- 2.1 Create a materials list and collect materials.
- 2.2 Identify materials and components and calculate quantities.
- 2.3 Check conformity of materials and components with delivery docket.
- 2.4 Sequence tasks.
- 2.5 Inspect site and determine location for fixed fire pumpset.
- 2.6 Carry out preparation of work area to ensure efficient installation.
- 2.7 Identify pump base requirements from drawings and specifications.
- 2.8 Select and check the serviceability of appropriate tools, equipment and personal protective equipment (PPE).
3 Install fixed fire pumpsets.
- 3.1 Set out and install pump base.
- 3.2 Perform the installation of pumpset, pipework and associated valves.
- 3.3 Check pipework, connections and pumpset valves to ensure they are watertight and operating correctly.
- 3.4 Pressure test piping system and record results.
- 3.5 Test pumpset and record test data in required format.
- 3.6 Complete documentation as required.
4 Clean up.
- 4.1 Clear the work area, and dispose of, reuse or recycle materials in accordance with state and territory legislation and workplace policies and procedures.
- 4.2 Clean tools and equipment, check for serviceability and report any damage, and store and secure.
No information
No information
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| WI771 | CPCPFS3048A | Install fixed fire pumpsets | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| BGC1 | CPC32820 | Certificate III in Fire Protection | Qualification |