Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Service and repair post hole digging systems

Service and repair post hole digging systems

Unit of competency
National Code
AURPTA108
State Code
OCL68
TGA Status
Current
DTWD Status
Approved
Current Release Number
1.00
Current Release Date
13/11/2020
State Implementation and Classification
Approved Date
31/03/2021
Field of Education
030701 - Mechanical Engineering
Original Release Date
31/03/2021
Nominal Hours
16
Description
This unit describes the skills and knowledge required to service and repair faults in the post hole digging systems of outdoor power equipment according to manufacturer specifications. The unit involves preparing for the task, determining the service and repair requirements, carrying out the service and repair, performing post-repair testing, and completing workplace processes and documentation.The unit applies to those working in the outdoor power equipment service and repair industry. The post hole digging systems may be powered by electric or internal combustion engines.No licensing, legislative, regulatory or certification requirements apply to this unit at the time of publication.
Notes
Elements and Performance Criteria
1. Prepare to service and repair post hole digging system
  • 1.1 Identify job requirements from workplace instructions
  • 1.2 Source and interpret workplace service and repair procedures
  • 1.3 Identify and manage hazards associated with the tasks
  • 1.4 Select tools and equipment and check for serviceability
2. Determine service and repair requirements of post hole digging system
  • 2.1 Inspect and test system according to manufacturer specifications, workplace procedures, and safety requirements
  • 2.2 Identify faults and determine causes of faults
  • 2.3 Report inspection findings and test results according to workplace procedures, and include recommendations for necessary service, repair or adjustment
  • 2.4 Obtain authorisation to proceed according to workplace procedures
3. Carry out service and repair activities
  • 3.1 Analyse service and repair options and select those most appropriate to the circumstances
  • 3.2 Select and check tools, equipment and materials
  • 3.3 Remove components and inspect for serviceability according to manufacturer specifications, workplace procedures, and safety requirements
  • 3.4 Fit and adjust reusable, repaired and replacement components according to manufacturer specifications and workplace procedures
4. Check post hole digging system for normal operation
  • 4.1 Operate and compare system according to manufacturer specifications, workplace procedures and safety requirements
  • 4.2 Make adjustments as required and re-test post hole digging system
5. Complete work processes
  • 5.1 Conduct final inspection according to workplace procedures and confirm equipment is ready for use
  • 5.2 Clear work area and dispose of or recycle materials according to workplace procedures
  • 5.3 Complete documentation according to workplace procedures
No information
No information
Replaces
State Code National Code Title Type