Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Coordinate plant shutdown
Coordinate plant shutdown
Unit of competency
National Code
PMAOPS522
PMAOPS522
State Code
AXM71
AXM71
TGA Status
Current
Current
DTWD Status
Approved
Approved
State Implementation and Classification
Approved Date
05/08/2016
Field of Education
030717 - Plant And Machine Operations
Original Release Date
05/08/2016
Nominal Hours
50
Description
This unit of competency covers the skills and knowledge required to coordinate a planned, major shutdown. A planned, major shutdown may be for whole plant/system, one plant area or one plant in an integrated complex and will typically occur to enable:regulatory vessel inspection (PVI)major maintenanceupgrades or refitscatalyst and/or column repackingother activities which are scheduled for the shutdown.This unit of competency applies to senior technicians or those in similar roles who are required to apply in-depth knowledge of process and plant operations and problem solving in order to coordinate shutdown sequence to ensure all process shutdown activities completed to schedule, coordinate the activities of a number of work groups, analyse/problem solve and develop contingency plans, and identify and coordinate resources and pre-shutdown requirements. This unit of competency applies to a plant technician who is performing the plant shutdown coordinator role as their primary activity. This technician would be part of a team working with technical experts, maintenance experts, contractor representatives, process/production teams and management. No licensing, legislative or certification requirements apply to this unit at the time of publication.
Notes
Elements and Performance Criteria
1 Identify shutdown work scope
- 1.1 Analyse relevant information for activities intended for the shutdown
- 1.2 Determine all activities intended for shutdown
- 1.3 Confirm priorities and identify all essential work
- 1.4 Resolve conflicts between proposed activities
2 Plan and schedule resources
- 2.1 Identify each individual task in the shutdown process
- 2.2 Determine resources required for each task and assign appropriate owner
- 2.3 Determine prerequisite tasks prior to shutting down process
- 2.4 Ensure hazards are identified and controls are in place
- 2.5 Ensure all safety and testing equipment is calibrated and on site prior to shutdown commencing
- 2.6 Compile a schedule to track shutdown and equipment preparation sequence
3 Coordinate plant/ equipment shutdown sequence
- 3.1 Prepare/review shutdown documentation
- 3.2 Coordinate plant shutdown according to procedures
- 3.3 Track plant shutdown progress
- 3.4 Coordinate execution of critical function test during shutdown phase
- 3.5 Coordinate equipment preparation
- 3.6 Validate equipment is safe to hand over to appropriate work party
4 Hand over plant/ equipment to relevant work party
- 4.1 Hand over plant and equipment to relevant work group according to site protocol
- 4.2 Perform safety audits during shutdown work
- 4.3 Record/report health, safety and environment (HSE) non-conformance
- 4.4 Communicate as and when required
- 4.5 Monitor shutdown work against critical path
- 4.6 Monitor resource usage and take action
- 4.7 Identify barriers to achieving shutdown critical path and negotiate solution
5 Communicate with all relevant stakeholders
- 5.1 Communicate shutdown plan/schedule to operations team
- 5.2 Attend and contribute to regular shutdown progress meetings
- 5.3 Record and report daily shutdown activities
- 5.4 Ensure all authorisations required for tasks have been obtained
- 5.5 Identify, communicate and mange HSE issues arising during execution of shutdown activities
- 5.6 Contribute to post shutdown review
6 Return plant to service
- 6.1 Confirm that all scheduled work on equipment is complete before hand back is accepted
- 6.2 Ensure equipment hand back documentation complete according to site protocol
- 6.3 Coordinate pre-start equipment integrity checks
- 6.4 Coordinate and validate plant de-isolation and preparation for service
- 6.5 Ensure appropriate plant start-up authority is obtained
- 6.6 Coordinate start-up critical function tests as required
- 6.7 Coordinate and record plant start-up progress
No information
No information
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| W8900 | PMAOPS522A | Coordinate plant shut down | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| BCU7 | PMC50116 | Diploma of Manufactured Mineral Products | Qualification |
| BCU5 | PMC60116 | Advanced Diploma of Manufactured Mineral Products | Qualification |
| BAN5 | PMA50116 | Diploma of Process Plant Technology | Qualification |
| BAM9 | PMA60116 | Advanced Diploma of Process Plant Technology | Qualification |