Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Implement a Just-in-Time (JIT) system
Implement a Just-in-Time (JIT) system
Unit of competency
National Code
ICPSU485C
ICPSU485C
State Code
D3280
D3280
TGA Status
Replaced
Replaced
DTWD Status
Replaced
Replaced
State Implementation and Classification
Approved Date
11/09/2014
Field of Education
089901 - Purchasing, Warehousing And Distribution
Original Release Date
11/09/2014
Nominal Hours
80
Description
This unit describes the performance outcomes, skills and knowledge required to facilitate the implementation and operation of a Just-in-Time (JIT)/kanban system in the organisation.
Notes
Elements and Performance Criteria
1. Monitor the operation of the JIT system
- 1.1. Track value of key measures
- 1.2. Recognise indicators of poor performance
- 1.3. Take appropriate quick fix action
2. Liaise with relevant stakeholders
- 2.1. Regularly communicate with team members regarding the operation of the JIT system
- 2.2. Communicate with relevant personnel up and down the value chain regarding the operation of the JIT system
- 2.3. Identify issues with stakeholders and take appropriate quick fix action
3. Improve the JIT system
- 3.1. Identify areas requiring improvement in the JIT system
- 3.2. Recognise competency gaps in team members and other stakeholders
- 3.3. Recognise attitudinal issues in team members and other stakeholders
- 3.4. Develop appropriate improvement solutions
- 3.5. Liaise with relevant people regarding these solutions
- 3.6. Implement/assist with the implementation of the solutions
RANGE STATEMENT
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Key measures may include:
key measures may include inventory levels, lead time, IFOTIS delivery, productivity/production rate, other measures of pull through the value chain, quality
IFOTIS refers to delivery of product In Full, On Time and In Specification.
Quick fix may include:
quick fix is action taken to immediately and cheaply control a problem, prevent it getting worse and/or ameliorate its impact, but which does not necessarily solve it long term.
JIT - Just-in-Time may include:
JIT - a production scheduling concept that calls for any item needed at a production operation, whether raw material, finished item, or anything in between, to be produced and available precisely when needed, neither a moment earlier nor a moment later.
Value chain may include:
competitive manufacturing organisations encompass the entire production system, beginning with the customer, and include the product sales outlet, the final assembler, product design, raw material mining and processing and all tiers of the value chain (sometimes called the supply chain). Any truly "competitive" system is highly dependent on the demands of its customers and the reliability of its suppliers. No implementation of competitive manufacturing can reach its full potential without including the entire "enterprise" in its planning.
Kanban may include:
Kanban - a card or sheet used to authorise production or movement of an item; when fully implemented, kanban (the plural is the same as the singular) operates according to the following rules:
all production and movement of parts and material take place only as required by a downstream operation, ie all manufacturing and procurement are ultimately driven by the requirements of final assembly or the equivalent
the specific tool which authorises production or movement is called a kanban. The word literally means card or sign, but it can legitimately refer to a container or other authorising device. Kanban have various formats and content as appropriate for their usage; for example, a kanban for a vendor is different than a kanban for an internal machining operation
Kanban is typically applied to batch type operation and the production is measured in units produced. In continuous manufacturing organisations, production is measured in terms of production rate (eg kg/h, tonne/day) and rate is increased/decreased according to the flow authorisation which may be a kanban (eg ticket, order from a supplier) or may be a SCADA signal from a remote facility (eg customer tank) saying that resupply is required or similar.
SCADA may include:
SCADA (System Control and Data Acquisition) is a general term applied to a number of systems which automatically collect critical process data, perform required mathematical manipulations on it and then make control decisions and/or give required information to personnel for action.
Pull system may include:
a manufacturing planning system based on communication of actual real-time needs from downstream operations ultimately final assembly or the equivalent; as opposed to a push system which schedules upstream operations according to theoretical downstream results based on a plan which may not be current.
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Key measures may include:
key measures may include inventory levels, lead time, IFOTIS delivery, productivity/production rate, other measures of pull through the value chain, quality
IFOTIS refers to delivery of product In Full, On Time and In Specification.
Quick fix may include:
quick fix is action taken to immediately and cheaply control a problem, prevent it getting worse and/or ameliorate its impact, but which does not necessarily solve it long term.
JIT - Just-in-Time may include:
JIT - a production scheduling concept that calls for any item needed at a production operation, whether raw material, finished item, or anything in between, to be produced and available precisely when needed, neither a moment earlier nor a moment later.
Value chain may include:
competitive manufacturing organisations encompass the entire production system, beginning with the customer, and include the product sales outlet, the final assembler, product design, raw material mining and processing and all tiers of the value chain (sometimes called the supply chain). Any truly "competitive" system is highly dependent on the demands of its customers and the reliability of its suppliers. No implementation of competitive manufacturing can reach its full potential without including the entire "enterprise" in its planning.
Kanban may include:
Kanban - a card or sheet used to authorise production or movement of an item; when fully implemented, kanban (the plural is the same as the singular) operates according to the following rules:
all production and movement of parts and material take place only as required by a downstream operation, ie all manufacturing and procurement are ultimately driven by the requirements of final assembly or the equivalent
the specific tool which authorises production or movement is called a kanban. The word literally means card or sign, but it can legitimately refer to a container or other authorising device. Kanban have various formats and content as appropriate for their usage; for example, a kanban for a vendor is different than a kanban for an internal machining operation
Kanban is typically applied to batch type operation and the production is measured in units produced. In continuous manufacturing organisations, production is measured in terms of production rate (eg kg/h, tonne/day) and rate is increased/decreased according to the flow authorisation which may be a kanban (eg ticket, order from a supplier) or may be a SCADA signal from a remote facility (eg customer tank) saying that resupply is required or similar.
SCADA may include:
SCADA (System Control and Data Acquisition) is a general term applied to a number of systems which automatically collect critical process data, perform required mathematical manipulations on it and then make control decisions and/or give required information to personnel for action.
Pull system may include:
a manufacturing planning system based on communication of actual real-time needs from downstream operations ultimately final assembly or the equivalent; as opposed to a push system which schedules upstream operations according to theoretical downstream results based on a plan which may not be current.
EVIDENCE GUIDE
The Evidence Guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment
Critical aspects for assessment and evidence required to demonstrate competency in this unit
Evidence of the ability to:
The competent team leader will at all times know the state of the JIT system in their area and will take actions to ensure its smooth operation on a day to day basis as well as recommend/undertake actions to improve it long term. Evidence should be available of the team leader's facilitation of the operation of the JIT system and their recommendations for making improvements
Evidence should be gathered from an extended period showing routine support for the JIT system and regular improvements made or recommended.
Context of and specific resources for assessment
Assessment must ensure:
this unit will need to be assessed in an organisation operating JIT
access to an organisation using JIT.
Method of assessment
A range of assessment methods should be used to assess practical skills and knowledge. The following examples are appropriate for this unit:
direct questioning combined with review of portfolios of evidence and third party workplace reports of on-the-job performance by the candidate.
Guidance information for assessment
Holistic assessment with other units relevant to the industry sector, workplace and job role is recommended.
The Evidence Guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment
Critical aspects for assessment and evidence required to demonstrate competency in this unit
Evidence of the ability to:
The competent team leader will at all times know the state of the JIT system in their area and will take actions to ensure its smooth operation on a day to day basis as well as recommend/undertake actions to improve it long term. Evidence should be available of the team leader's facilitation of the operation of the JIT system and their recommendations for making improvements
Evidence should be gathered from an extended period showing routine support for the JIT system and regular improvements made or recommended.
Context of and specific resources for assessment
Assessment must ensure:
this unit will need to be assessed in an organisation operating JIT
access to an organisation using JIT.
Method of assessment
A range of assessment methods should be used to assess practical skills and knowledge. The following examples are appropriate for this unit:
direct questioning combined with review of portfolios of evidence and third party workplace reports of on-the-job performance by the candidate.
Guidance information for assessment
Holistic assessment with other units relevant to the industry sector, workplace and job role is recommended.
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| D0530 | ICPSU485B | Implement a Just-in-Time (JIT) system | Unit of competency |
Replaced By
| State Code | National Code | Title | Type |
|---|---|---|---|
| AUM72 | ICPSUP485 | Implement a Just-in-Time system | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| J183 | ICP30412 | Certificate III in Printing and Graphic Arts (Digital Printing) | Qualification |
| W790 | ICP50110 | Diploma of Printing and Graphic Arts (Digital Production) | Qualification |
| W787 | ICP40510 | Certificate IV in Printing and Graphic Arts (Mail House) | Qualification |
| W793 | ICP50410 | Diploma of Printing and Graphic Arts (Management/Sales) | Qualification |
| W786 | ICP40410 | Certificate IV in Printing and Graphic Arts (Print Finishing) | Qualification |
| W785 | ICP40310 | Certificate IV in Printing and Graphic Arts (Printing) | Qualification |
| W794 | ICP50510 | Diploma of Printing and Graphic Arts (Process Improvement) | Qualification |
| W789 | ICP40710 | Certificate IV in Printing and Graphic Arts (Process Leadership) | Qualification |