Unit of competency Outline

Date retreived
22/07/2026 6:19 AM AWST

Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Deliver concrete to site

Deliver concrete to site

Unit of competency
National Code
PMC552061
State Code
BAH36
TGA Status
Replaced
DTWD Status
Replaced
Current Release Number
1.00
Current Release Date
22/06/2016
State Implementation and Classification
Approved Date
05/08/2016
Field of Education
030717 - Plant And Machine Operations
Original Release Date
05/08/2016
Nominal Hours
30
Description
This unit of competency covers the skills and knowledge required to deliver concrete to site using an agitator or similar.This unit of competency applies to operators who are required to safely drive and position the agitator truck, load agitator, mix and discharge concrete on site, communicate with customers and rectify routine problems.This unit of competency applies to an individual working independently and with frequent contact with the base plant personnel.The operator is required to hold a current driver’s license appropriate to the agitator truck as required by local regulations.
Notes
Elements and Performance Criteria
1 Load agitator
  • 1.1 Check job requirements
  • 1.2 Position agitator for loading
  • 1.3 Load agitator with correct concrete batch
  • 1.4 Check any special requirements and take action required
  • 1.5 Check that slump is to specification and take any action required
2 Deliver concrete
  • 2.1 Deliver concrete without delay
  • 2.2 Position vehicle/agitator as required by safety needs and if practical customer requirements
  • 2.3 Report breakdowns or lengthy delays en route to relevant person
  • 2.4 Maintain product quality as per requirements and procedures
3 Conform to site protocols
  • 3.1 Check access to site with customer
  • 3.2 Assess site conditions and enter in a manner suited to the conditions, load and site requirements
  • 3.3 Mix concrete on site according to quality requirements
  • 3.4 Discharge concrete as required by customer
  • 3.5 Wash down chutes and agitator in the area designated by the customer
  • 3.6 Complete all records
4 Rectify routine problems
  • 4.1 Identify the range of faults that can occur during the operation
  • 4.2 Determine and rectify fault causes in accordance with procedures/work instructions
  • 4.3 Identify and rectify equipment failure causes in accordance with procedures
  • 4.4 Make sure appropriate records and log books of equipment operations are maintained to meet procedures
  • 4.5 Identify non-routine problems and take appropriate action.
  • 4.6 Ensure required checklists are completed
5 Control hazards
  • 5.1 Identify hazards from the job to be done
  • 5.2 Identify other hazards in the work area
  • 5.3 Assess the risks arising from those hazards
  • 5.4 Implement measures to control those risks in line with procedures
No information
No information
Replaces
State Code National Code Title Type
WA946 PMC552061C Deliver concrete to site Unit of competency
Replaced By
State Code National Code Title Type
OAE97 MSMPMC322 Deliver concrete to site Unit of competency