Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Select and manage building and construction contractors
Select and manage building and construction contractors
Unit of competency
National Code
CPCCBC5005A
CPCCBC5005A
State Code
W9292
W9292
TGA Status
Replaced
Replaced
DTWD Status
Replaced
Replaced
State Implementation and Classification
Approved Date
10/08/2012
Field of Education
040303 - Building Construction Management
Original Release Date
10/08/2012
Nominal Hours
40
Description
This unit of competency specifies the outcomes required to select and manage building and construction contractors.It covers the processes and practices involved in supervising the systems through which the selection and management of subcontract resources occurs within the organisation, and through which subcontracting needs are identified and quantified. In order to achieve the outcomes for this unit, knowledge of relevant industry legislation, standards and codes, the subcontracting system and industrial relations processes is required.
Notes
Elements and Performance Criteria
1. Manage the determination of subcontractor requirements.
- 1.1. Subcontractor resource requirements are assessed on the basis of expected operations and reference to the business plan.
- 1.2. Subcontractor requirements are managed, prioritised and documented on the basis of expected work sequence and volume.
- 1.3. Task analyses are conducted and managed and competences are identified from the nature of the work to be done and organisational structure.
- 1.4. Type and number of subcontractors are determined and a formal subcontractor structure is developed for the project.
- 1.5. Industrial legislation and contract legal matters that impact on operations are researched to clarify workplace obligations and subcontractor rights.
2. Manage the review of subcontractor performance.
- 2.1. Existing subcontractor areas of expertise are identified or reviewed to build an operational profile for each subcontractor.
- 2.2. Information is gathered and examined on previous performance of existing subcontractors, their work profiles and history.
- 2.3. Reviewing subcontractor performance for the purpose of identifying strengths and weaknesses is undertaken.
- 2.4. Management plan is developed for each subcontractor to enhance their ability to meet contractual obligations.
3. Establish terms and conditions for subcontractor engagement.
- 3.1. Subcontractor terms of engagement and scope of operations under the contract are developed or reviewed to ensure contract obligations can be met.
- 3.2. Conditions to be met under the terms of engagement for subcontractors are reviewed and periodically reinforced with the subcontractors.
4. Manage the selection and engagement of subcontractors.
- 4.1. Subcontractor engagement strategies and processes are developed and facilitated to meet organisational timelines and contract dates.
- 4.2. Processes for selection and engagement of subcontractors are managed to ensure that equal opportunity principles apply to all applicants.
- 4.3. Subcontractor short-listing and qualification checking are managed to enable the selection and engagement of the most appropriate subcontractor.
- 4.4. Successful and unsuccessful tenderers are notified about the outcomes of the selection process.
- 4.5. Processes for commencement, induction and any required pre-engagement training are managed and implemented.
5. Evaluate subcontractor performance and compliance with contract requirements.
- 5.1. Systems that evaluate subcontractor performance and compliance with contract requirements are developed and managed.
- 5.2. Gathering of strategic information about subcontractor performance is managed under terms of confidentiality and security but within known collection parameters.
- 5.3. Performance review outcomes are discussed with subcontractors on a confidential and equitable basis.
- 5.4. Feedback and appeal systems are introduced and managed to ensure that subcontractors have the opportunity to challenge review outcomes.
- 5.5. Remedial or disciplinary action is undertaken against the subcontractor in accordance with organisational policy and operational guidelines where appropriate.
RANGE STATEMENT
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Subcontractor requirements include:
calculating number of subcontractors required by the hours within the timeframe
calculating quantum of hours required to perform the work
determining total hours required for each function and stage of work
estimating project timeframe from start to finish
identifying work sequence and nature of job roles.
Reviewing subcontractor performance includes:
anecdotal evidence, including input from project managers and administrators
examination of data provided by the subcontractor
input about subcontractor performance from other organisations
observation of the subcontractor on other project sites
using subcontractor performance records from previous associations.
Selection and engagement of subcontractors include:
advising interviewees of the outcome of the selection process
arranging credit checks to determine subcontractor financial viability
ensuring selection interviews with subcontractors meet the criteria
providing invitations to tender for subcontract opportunities
reviewing tender responses and checking referees
undertaking contractual arrangements between the organisation and successful subcontractors.
Subcontractor performance and compliance with contract requirements include:
establishment of performance benchmarks within subcontracts
participation by subcontractors in project meetings and provision of progress reports
performance management where performance is sub-standard or inappropriate
performance monitoring against project timelines and objectives
regular communication with subcontractors.
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Subcontractor requirements include:
calculating number of subcontractors required by the hours within the timeframe
calculating quantum of hours required to perform the work
determining total hours required for each function and stage of work
estimating project timeframe from start to finish
identifying work sequence and nature of job roles.
Reviewing subcontractor performance includes:
anecdotal evidence, including input from project managers and administrators
examination of data provided by the subcontractor
input about subcontractor performance from other organisations
observation of the subcontractor on other project sites
using subcontractor performance records from previous associations.
Selection and engagement of subcontractors include:
advising interviewees of the outcome of the selection process
arranging credit checks to determine subcontractor financial viability
ensuring selection interviews with subcontractors meet the criteria
providing invitations to tender for subcontract opportunities
reviewing tender responses and checking referees
undertaking contractual arrangements between the organisation and successful subcontractors.
Subcontractor performance and compliance with contract requirements include:
establishment of performance benchmarks within subcontracts
participation by subcontractors in project meetings and provision of progress reports
performance management where performance is sub-standard or inappropriate
performance monitoring against project timelines and objectives
regular communication with subcontractors.
EVIDENCE GUIDE
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment
This unit of competency could be assessed by effective selection and management of building and construction contractors for medium rise projects against projected organisational activities and the business plan.
This unit of competency can be assessed in the workplace or a close simulation of the workplace environment, provided that simulated or project-based assessment techniques fully replicate construction workplace conditions, materials, activities, responsibilities and procedures.
Critical aspects for assessment and evidence required to demonstrate competency in this unit
A person who demonstrates competency in this unit must be able to provide evidence of the ability to:
identify the subcontractor needs of the organisation based on an evaluation of organisation's projected work load and forward contractual commitments
assess the extent of effective systems introduced to review subcontractor performance and competency
implement an effective and efficient appointments process
implement an effective and efficient management of the system of subcontractor appointments to meet project timeframes
demonstrate remedial or disciplinary action for below standard subcontractor performance.
Context of and specific resources for assessment
This competency is to be assessed using standard and authorised work practices, safety requirements and environmental constraints.
Assessment of essential underpinning knowledge will usually be conducted in an off-site context.
Assessment is to comply with relevant regulatory or Australian standards' requirements.
Resource implications for assessment include:
documentation that should normally be available in either a building or construction office
relevant codes, standards and regulations
office equipment, including calculators, photocopiers and telephone systems
computers with appropriate software to view 2-D CAD drawings, run costing programs and print copies
a technical reference library with current publications on measurement, design, building construction and manufacturers' product literature
copies of appropriate awards and workplace agreements
a suitable work area appropriate to this process.
Reasonable adjustments for people with disabilities must be made to assessment processes where required. This could include access to modified equipment and other physical resources, and the provision of appropriate assessment support.
Method of assessment
Assessment methods must:
satisfy the endorsed Assessment Guidelines of the Construction, Plumbing and Services Training Package
include direct observation of tasks in real or simulated work conditions, with questioning to confirm the ability to consistently identify and correctly interpret the essential underpinning knowledge required for practical application
reinforce the integration of employability skills with workplace tasks and job roles
confirm that competency is verified and able to be transferred to other circumstances and environments.
Validity and sufficiency of evidence requires that:
competency will need to be demonstrated over a period of time reflecting the scope of the role and the practical requirements of the workplace
where the assessment is part of a structured learning experience the evidence collected must relate to a number of performances assessed at different points in time and separated by further learning and practice, with a decision on competency only taken at the point when the assessor has complete confidence in the person's demonstrated ability and applied knowledge
all assessment that is part of a structured learning experience must include a combination of direct, indirect and supplementary evidence.
Assessment processes and techniques should as far as is practical take into account the language, literacy and numeracy capacity of the candidate in relation to the competency being assessed.
Supplementary evidence of competency may be obtained from relevant authenticated documentation from third parties, such as existing supervisors, team leaders or specialist training staff.
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment
This unit of competency could be assessed by effective selection and management of building and construction contractors for medium rise projects against projected organisational activities and the business plan.
This unit of competency can be assessed in the workplace or a close simulation of the workplace environment, provided that simulated or project-based assessment techniques fully replicate construction workplace conditions, materials, activities, responsibilities and procedures.
Critical aspects for assessment and evidence required to demonstrate competency in this unit
A person who demonstrates competency in this unit must be able to provide evidence of the ability to:
identify the subcontractor needs of the organisation based on an evaluation of organisation's projected work load and forward contractual commitments
assess the extent of effective systems introduced to review subcontractor performance and competency
implement an effective and efficient appointments process
implement an effective and efficient management of the system of subcontractor appointments to meet project timeframes
demonstrate remedial or disciplinary action for below standard subcontractor performance.
Context of and specific resources for assessment
This competency is to be assessed using standard and authorised work practices, safety requirements and environmental constraints.
Assessment of essential underpinning knowledge will usually be conducted in an off-site context.
Assessment is to comply with relevant regulatory or Australian standards' requirements.
Resource implications for assessment include:
documentation that should normally be available in either a building or construction office
relevant codes, standards and regulations
office equipment, including calculators, photocopiers and telephone systems
computers with appropriate software to view 2-D CAD drawings, run costing programs and print copies
a technical reference library with current publications on measurement, design, building construction and manufacturers' product literature
copies of appropriate awards and workplace agreements
a suitable work area appropriate to this process.
Reasonable adjustments for people with disabilities must be made to assessment processes where required. This could include access to modified equipment and other physical resources, and the provision of appropriate assessment support.
Method of assessment
Assessment methods must:
satisfy the endorsed Assessment Guidelines of the Construction, Plumbing and Services Training Package
include direct observation of tasks in real or simulated work conditions, with questioning to confirm the ability to consistently identify and correctly interpret the essential underpinning knowledge required for practical application
reinforce the integration of employability skills with workplace tasks and job roles
confirm that competency is verified and able to be transferred to other circumstances and environments.
Validity and sufficiency of evidence requires that:
competency will need to be demonstrated over a period of time reflecting the scope of the role and the practical requirements of the workplace
where the assessment is part of a structured learning experience the evidence collected must relate to a number of performances assessed at different points in time and separated by further learning and practice, with a decision on competency only taken at the point when the assessor has complete confidence in the person's demonstrated ability and applied knowledge
all assessment that is part of a structured learning experience must include a combination of direct, indirect and supplementary evidence.
Assessment processes and techniques should as far as is practical take into account the language, literacy and numeracy capacity of the candidate in relation to the competency being assessed.
Supplementary evidence of competency may be obtained from relevant authenticated documentation from third parties, such as existing supervisors, team leaders or specialist training staff.
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| W5938 | BCGBC5005A | Select and manage building and construction contractors | Unit of competency |
Replaced By
| State Code | National Code | Title | Type |
|---|---|---|---|
| OCP23 | CPCCBC5005 | Select and manage building and construction contractors | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| W741 | CPC50210 | Diploma of Building and Construction (Building) | Qualification |
| W616 | CPC50308 | Diploma of Building and Construction (Management) | Qualification |
| D772 | CPP50911 | Diploma of Building Design | Qualification |