Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Install temporary and permanent rock anchors
Install temporary and permanent rock anchors
Unit of competency
National Code
RIICFW302D
RIICFW302D
State Code
WH093
WH093
TGA Status
Replaced
Replaced
DTWD Status
Replaced
Replaced
State Implementation and Classification
Approved Date
29/05/2014
Field of Education
040301 - Building Science And Technology
Original Release Date
29/05/2014
Nominal Hours
20
Description
This unit describes a participant’s skills and knowledge required to install temporary and permanent rock anchors in Civil Construction.This unit is appropriate for those working in operational roles. No licensing or certification requirements apply to this unit at the time of publication.
Notes
Elements and Performance Criteria
1. Plan and prepare for rock anchor installation
- 1.1 Access, interpret and apply rock anchor installation documentation and ensure the work activity is compliant
- 1.2 Obtain, interpret and clarify work instructions before proceeding
- 1.3 Confirm and apply environmental protection and safety requirements
- 1.4 Obtain, interpret and implement traffic management signage requirements
- 1.5 Select, and check for faults, plant, tools and equipment to carry out tasks
- 1.6 Select and wear personal protective equipment appropriate for work activities
- 1.7 Identify, address and report potential hazards and risks
- 1.8 Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency
2. Set up and prepare anchor holes
- 2.1 Ensure holes are drilled to specified diameter and depth
- 2.2 Ensure holes are cleaned
- 2.3 Ensure bond length of holes for permanent anchors are tested for leakage to specified rate and grouted, re-drilled and retested
- 2.4 Ensure holes are temporarily covered to prevent entry of foreign material
3. Install anchors to anchor holes
- 3.1 Check components to verify conformity with job requirements
- 3.2 Grease, sheathe and assemble anchors to specifications
- 3.3 Prepare temporary anchors with spacers and fit grout tubes
- 3.4 Prepare permanent anchors with spacers, fit grout tubes and prepare external polyethylene sheath
- 3.5 Install anchors and sheaths to full depth, without damage and to specifications
- 3.6 Set up grouting plant and flow monitoring apparatus to design requirements
- 3.7 Mix and pump grout into hole
4. Set up anchorage assembly and stress anchors
- 4.1 Position anchorage using packing materials
- 4.2 Stress anchors to nominated loads
- 4.3 Lock off anchors to nominated loads
- 4.4 Install mesh to job specification
- 4.5 Apply shotcrete to design depth, tolerance and job specification
- 4.6 Monitor permanent anchors at scheduled intervals, and determine and record anchor’s residual load
- 4.7 Cut anchors where required and seal
5. Clean up
- 5.1 Clear work area and dispose of/or recycle materials
- 5.2 Clean, check, maintain and store plant, tools and equipment
No information
No information
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| WB260 | RIICFW302A | Install temporary and permanent rock anchors | Unit of competency |
Replaced By
| State Code | National Code | Title | Type |
|---|---|---|---|
| OCX31 | RIICFW302E | Install temporary and permanent rock anchors | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| BFA8 | RII30919 | Certificate III in Civil Construction | Qualification |
| AZB0 | RII30915 | Certificate III in Civil Construction | Qualification |
| AZE0 | RII31215 | Certificate III in Civil Foundations | Qualification |
| J634 | RII31213 | Certificate III in Civil Foundations | Qualification |
| J488 | CPC31712 | Certificate III in Post-Tensioning | Qualification |