Unit of competency Outline

Date retreived
22/07/2026 11:25 PM AWST

Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Manage IT project closure

Manage IT project closure

Unit of competency
National Code
ICAPMG605A
State Code
D7926
TGA Status
Replaced
DTWD Status
Replaced
Current Release Number
1.00
Current Release Date
18/07/2011
State Implementation and Classification
Approved Date
26/03/2012
Field of Education
080315 - Project Management
Original Release Date
26/03/2012
Nominal Hours
40
Description
This unit describes the performance outcomes, skills and knowledge required to decommission or close an information technology (IT) project within a small, medium or large organisation.
Notes
Elements and Performance Criteria
1. Evaluate project performance
  • 1.1 Collect project performance metrics
  • 1.2 Debrief project team
  • 1.3 Debrief project stakeholders
  • 1.4 Summarise and report on results
2. Finalise the project
  • 2.1 Review project performance to determine whether the project should be continued, decommissioned or closed
  • 2.2 Assess the impact of continuing, decommissioning or closing the project
  • 2.3 Recommend appropriate management action to the relevant governing authority
  • 2.4 Decommission or close the project if required
3. Action outstanding activities
  • 3.1 Identify outstanding activities and create an action plan
  • 3.2 Assign responsibilities to action outstanding activities
  • 3.3 Follow up outstanding activities to ensure completion
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.

Project performance metrics may include:
financial measures:
actual versus planned budget
actual versus planned return on investment (RoI) projections
earned value (EV) and EV performance indexes
quality measures:
number of defects
stakeholder satisfaction feedback
scope measures:
actual versus expected number of change requests
amount of rework
requirements or user story backlogs
time measures:
actual versus expected burn-down rates
planned versus actual schedule.
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.

Overview of assessment

Critical aspects for assessment and evidence required to demonstrate competency in this unit
Evidence of the ability to:
recommend and plan the decommissioning or closure of a complex IT project based on collected performance metrics.
Context of and specific resources for assessment
Assessment must ensure access to:
appropriate learning and assessment support when required
modified equipment for people with special needs
relevant project documentation, including project metrics
project stakeholders.
Method of assessment
A range of assessment methods should be used to assess practical skills and knowledge. The following examples are appropriate for this unit:
preferred assessment method is through a workplace project or through a simulated medium to large enterprise workplace
direct observation of the candidate carrying out project work
verbal or written questioning to assess required knowledge and skills
review of reports, documents and presentations
review of a portfolio of the project work undertaken.
Guidance information for assessment
Holistic assessment with other units relevant to the industry sector, workplace and job role is recommended, where appropriate.
Assessment processes and techniques must be culturally appropriate, and suitable to the communication skill level, language, literacy and numeracy capacity of the candidate and the work being performed.
Indigenous people and other people from a non-English speaking background may need additional support.
In cases where practical assessment is used it should be combined with targeted questioning to assess required knowledge.
Replaced By
State Code National Code Title Type
AUV45 ICTPMG605 Manage ICT project closure Unit of competency
State Code National Code Title Type
D579 ICA60411 Advanced Diploma of Information Technology Project Management Qualification