Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Conduct road pavement construction

Conduct road pavement construction

Unit of competency
National Code
RIICRC307A
State Code
WB440
TGA Status
Replaced
DTWD Status
Replaced
Current Release Number
1.00
Current Release Date
22/06/2011
State Implementation and Classification
Approved Date
20/01/2010
Field of Education
030901 - Construction Engineering
Original Release Date
20/01/2010
Nominal Hours
20
Description
This unit covers the conduct of road pavement construction in the civil construction industry. It includes planning and preparing for work, setting out sub-base/bases, placing and spreading materials, compacting materials, and cleaning up. Licensing, legislative, regulatory and certification requirements that apply to this unit can vary between states, territories, and industry sectors. Relevant information must be sourced prior to application of the unit.
Notes
Elements and Performance Criteria
1. Plan and prepare work
  • 1.1. Access, interpret and apply compliance documentation relevant to the work activity
  • 1.2. Obtain and confirm safety requirements from the site safety plan and organisational policies and procedures, and apply to the allotted task
  • 1.3. Identify, obtain and implement signage requirements from the project traffic management plan
  • 1.4. Select plant, tools and equipment to carry out tasks consistent with the requirements of the job, check for serviceability and rectify or report any faults
  • 1.5. Identify environmental protection requirements from the project environmental management plan, and confirm and apply to the allotted task
2. Set out sub-base/base
  • 2.1. Set out job to plan from survey controls
  • 2.2. Establish offset pegs/profiles to line and level as specified
3. Place and spread materials
  • 3.1. Determine layer depth for spreading materials and inform plant operators accordingly
  • 3.2. Direct trucks to correct location and specify the method of dispatching for load placement
  • 3.3. Check moisture content of materials and adjust uniformly
  • 3.4. Assess road pavement laying to ensure specified heights and the overall dimensions are achieved
4. Compact materials
  • 4.1. Inform roller operators of the required number of passes
  • 4.2. Assess compaction process to ensure the nominated number of passes are made to achieve uniform compaction across the pavement
  • 4.3. Check pavement trimming to ensure specified tolerances are achieved
5. Clean up
  • 5.1. Clear work area and dispose of or recycle materials in accordance with project environmental management plan
  • 5.2. Clean, check, maintain and store plant, tools and equipment
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Relevant compliance documentation may include:
legislative, organisational and site requirements and procedures
manufacturer's guidelines and specifications
Australian standards
Employment and workplace relations legislation
Equal Employment Opportunity and Disability Discrimination legislation
Safety requirements may include:
OHS requirements in accordance with state or territory legislation and regulations, organisational safety policies and procedures, and project safety plan, including protective clothing and equipment, use of tools and equipment, workplace environment and safety, handling of materials, use of fire fighting equipment, use of First Aid equipment, hazard control and hazardous materials and substances
safe operating procedures including recognising and preventing hazards associated with high voltage power lines, uneven/unstable terrain, trees, overhead service lines, bridges, surrounding buildings, obstructions, structures, facilities, dangerous materials, recently filled trenches, other machines, personnel, traffic control, working at heights, working in proximity to others, worksite visitors and the public
safe parking practices including ensuring access ways are clear, equipment/machinery is away from overhangs and refuelling sites, safe distances are kept from excavations, and areas secured from unauthorised access or movement
recognising hazards and risks including uneven/unstable terrain, trees, fires, overhead and underground services, bridges, buildings, excavations, traffic, embankments, cuttings, structures and hazardous materials
emergency procedures related to equipment operation including emergency shutdown and stopping, extinguishing equipment fires, organisational First Aid requirements and evacuation
Site may include:
haul roads
formed/prepared roads
access roads
pads
dam walls
Plant may include:
rollers
graders
skid-steers
backhoes
paver
excavators
front-end loaders
tip-trucks
water carts
Tools and equipment may include:
shovels
levelling equipment
string lines
crowbars
tape measures
handsaws
cutting knives
hammers
trowels
formwork
Environmental protection requirements may include:
organisational/project environmental management plan
waste management
water quality protection
noise
vibration
dust and clean-up management
Line and level may include:
the use of a string line
Materials may include:
gravel
rock
sand
blended materials
stabilised materials
quarried products
Road pavement may include:
all the materials above the sub-grade and below the wearing surface
may also be known as sub-base and/or base structure
Construction of road pavement may include:
surface finish
the repair of surface defects

The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment

Critical aspects for assessment and evidence required to demonstrate competency in this unit
The evidence required to demonstrate competency in this unit must be relevant to worksite operations and satisfy all of the requirements of the performance criteria, required skills and knowledge and the range statement of this unit and include evidence of the following:
knowledge of the requirements, procedures and instructions for conducting road pavement construction
implementation of requirements, procedures and techniques for the safe, effective and efficient completion of road pavement construction
working with others to undertake and complete the conduct of road pavement construction that meets all of the required outcomes
consistent timely completion of road pavement construction that safely, effectively and efficiently meets the required outcomes
completion of the construction of a road pavement including the following, with the results gaining acceptance as being to specification:
set out of base
placement and spreading of materials
compaction of materials
Context of and specific resources for assessment
This unit must be assessed in the context of the work environment. Where personal safety or environmental damage are limiting factors, assessment may occur in a simulated environment provided it is realistic and sufficiently rigorous to cover all aspects of workplace performance, including task skills, task management skills, contingency management skills and job role environment skills.
Assessment of this competency requires typical resources normally used in a resources and infrastructure sector environment. Selection and use of resources for particular worksites may differ due to the site circumstances.
The assessment environment should not disadvantage the participant. For example, language, literacy and numeracy demands of assessment should not be greater than those required on the job.
Customisation of assessment and delivery environment to sensitively accommodate cultural diversity.
Aboriginal people and other people from a non English speaking background may have second language issues.
Where applicable, physical resources should include equipment modified for people with disabilities. Access must be provided to appropriate learning and/or assessment support when required.
Method of assessment
This unit may be assessed in a holistic way with other units of competency. The assessment strategy for this unit must verify required knowledge and skill and practical application using more than one of the following assessment methods:
written and/or oral assessment of the candidate's required knowledge
observed, documented and/or first hand testimonial evidence of the candidate's:
implementation of appropriate requirement, procedures and techniques for the safe, effective and efficient achievement of required outcomes
consistent achievement of required outcomes
first hand testimonial evidence of the candidate's:
working with others to undertake and complete the conduct of road pavement construction
Guidance information for assessment
Consult the SkillsDMC User Guide for further information on assessment including access and equity issues.

Replaces
State Code National Code Title Type
W2113 BCCRC3007B Conduct road pavement construction Unit of competency
Replaced By
State Code National Code Title Type
WH123 RIICRC307D Conduct road pavement construction Unit of competency
State Code National Code Title Type
W678 RII31409 Certificate III in Road Construction and Maintenance Qualification