Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Apply project cost-management techniques
Apply project cost-management techniques
Unit of competency
National Code
BSBPMG412A
BSBPMG412A
State Code
WG091
WG091
TGA Status
Replaced
Replaced
DTWD Status
Replaced
Replaced
State Implementation and Classification
Approved Date
28/06/2013
Field of Education
080315 - Project Management
Original Release Date
28/06/2013
Nominal Hours
40
Description
This unit describes the performance outcomes, skills and knowledge required to assist in producing a project budget, to monitor project expenditure and to contribute to cost finalisation processes.
Notes
Elements and Performance Criteria
1. Assist in developing the project budget
- 1.1 Implement cost-estimating methods against duration/effort and resource requirements
- 1.2 Determine estimated costs for tasks and activities and confirm degree of accuracy with relevant stakeholders
- 1.3 Communicate cost estimates where required to others to contribute to project budget and cash flow management
- 1.4 Contribute to developing cost-management strategies and processes, and providing financial authorisation within delegated authority
2. Monitor project costs
- 2.1 Monitor income and expenditure against the project budget baseline at predetermined intervals
- 2.2 Identify and report variations in the budget using established project cost methods, techniques and tools
- 2.3 Implement action and report progress to ensure cost objectives remain achievable throughout the project life cycle
3. Contribute to cost-finalisation process
- 3.1 Assist in the finalisation and transfer of financial assets, liabilities and records to relevant parties
- 3.2 Assist in the review of project outcomes through the use of project cost records to determine the effectiveness of cost-management processes
- 3.3 Document cost-management lessons learned for application to future projects
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Cost-estimating methods may include:
allowance for contingency and risk
cost of quality (COQ)
expert opinion
organisational budget and cost-control policy
organisational chart of accounts
parametric estimating
prior project history
reserve analysis
review of organisational records
top-down or bottom-up estimating.
Cost estimates may include:
application and registration fees for intellectual property (IP) and patents
contingencies identified in risk assessment
facilities
fixed costs
labour
material
project-management overheads
services
travel and accommodation
variable costs.
Others may include:
higher project authority
organisation finance controller
project manager
project specialists and other personnel
relevant accounting support personnel
team members.
Project cost methods, techniques and tools may include:
communication with stakeholders
dispute-resolution and modification procedures
implementation of financial control mechanisms
industry standard cost-management software
integration with organisational finance systems
organisational procurement policy
measurement of actual progress against planned milestones
preferred and pre-qualified supplier costs
project accounting methods
recording and reporting of variations.
Implement action may include:
revised budget forecasts
under limited guidance and supervision
variance management
within agreed authorisation and limits
within established organisational framework, procedures and routines.
Project cost records may include:
cost-management lessons learned
cost verification and validation documentation
input to cost-management plans
invoice and payment records
lists of potential costs
project and/or organisation files and records
reports to relevant stakeholders.
Cost-estimating methods may include:
allowance for contingency and risk
cost of quality (COQ)
expert opinion
organisational budget and cost-control policy
organisational chart of accounts
parametric estimating
prior project history
reserve analysis
review of organisational records
top-down or bottom-up estimating.
Cost estimates may include:
application and registration fees for intellectual property (IP) and patents
contingencies identified in risk assessment
facilities
fixed costs
labour
material
project-management overheads
services
travel and accommodation
variable costs.
Others may include:
higher project authority
organisation finance controller
project manager
project specialists and other personnel
relevant accounting support personnel
team members.
Project cost methods, techniques and tools may include:
communication with stakeholders
dispute-resolution and modification procedures
implementation of financial control mechanisms
industry standard cost-management software
integration with organisational finance systems
organisational procurement policy
measurement of actual progress against planned milestones
preferred and pre-qualified supplier costs
project accounting methods
recording and reporting of variations.
Implement action may include:
revised budget forecasts
under limited guidance and supervision
variance management
within agreed authorisation and limits
within established organisational framework, procedures and routines.
Project cost records may include:
cost-management lessons learned
cost verification and validation documentation
input to cost-management plans
invoice and payment records
lists of potential costs
project and/or organisation files and records
reports to relevant stakeholders.
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment
Critical aspects for assessment and evidence required to demonstrate competency in this unit
Evidence of the following is essential:
applying cost-management techniques in relation to project budgets
reviewing project cost-management outcomes
communicating project cost budget to others effectively
knowledge of cost-management tools and techniques.
Context of and specific resources for assessment
Assessment must ensure access to:
examples of project-management budgets and related financial documentation
evidence or project records of involvement in cost-management processes.
Method of assessment
A range of assessment methods should be used to assess practical skill and knowledge. The following assessment methods are appropriate for this unit:
direct questioning combined with review of portfolios of evidence and third-party workplace reports of on-the-job performance by the candidate
analysis of responses addressing different project cost-management scenarios
oral or written questioning to assess knowledge of strategies for managing project costs
analysis of budgets and costing prepared by the candidate
review of communication to others of estimated costs for tasks and activities for inclusion in project budget
evaluation of reporting on cost-management issues and responses to project or program manager.
Guidance information for assessment
Holistic assessment with other units relevant to the industry sector, workplace and job role is recommended.
Overview of assessment
Critical aspects for assessment and evidence required to demonstrate competency in this unit
Evidence of the following is essential:
applying cost-management techniques in relation to project budgets
reviewing project cost-management outcomes
communicating project cost budget to others effectively
knowledge of cost-management tools and techniques.
Context of and specific resources for assessment
Assessment must ensure access to:
examples of project-management budgets and related financial documentation
evidence or project records of involvement in cost-management processes.
Method of assessment
A range of assessment methods should be used to assess practical skill and knowledge. The following assessment methods are appropriate for this unit:
direct questioning combined with review of portfolios of evidence and third-party workplace reports of on-the-job performance by the candidate
analysis of responses addressing different project cost-management scenarios
oral or written questioning to assess knowledge of strategies for managing project costs
analysis of budgets and costing prepared by the candidate
review of communication to others of estimated costs for tasks and activities for inclusion in project budget
evaluation of reporting on cost-management issues and responses to project or program manager.
Guidance information for assessment
Holistic assessment with other units relevant to the industry sector, workplace and job role is recommended.
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| D0923 | BSBPMG403A | Apply cost management techniques | Unit of competency |
Replaced By
| State Code | National Code | Title | Type |
|---|---|---|---|
| AUK33 | BSBPMG412 | Apply project cost management techniques | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| J831 | AUM40113 | Certificate IV in Automotive Manufacturing | Qualification |
| J519 | BSB41513 | Certificate IV in Project Management Practice | Qualification |