Unit of competency Outline
Date retreived
23/07/2026 4:28 PM AWST
23/07/2026 4:28 PM AWST
Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Lift and move load using a mobile crane
Lift and move load using a mobile crane
Unit of competency
National Code
TLID3036
TLID3036
State Code
AWM55
AWM55
TGA Status
Current
Current
DTWD Status
Approved
Approved
State Implementation and Classification
Approved Date
04/08/2016
Field of Education
030717 - Plant And Machine Operations
Original Release Date
04/08/2016
Nominal Hours
40
Description
This unit involves the skills and knowledge required to lift and move a load using a mobile crane. It includes operating a non-slewing or slewing mobile crane to complete job requirements, monitoring lift conditions, implementing shutdown procedures, packing up crane after operations and completing all required job records.People achieving competence in this unit will need to fulfil the applicable state or territory legislated high-risk work licence requirements and to comply with relevant codes of practice and guidelines for mobile crane operations.Work is performed with limited supervision and duty of care responsibility for self and others in achieving the prescribed outcomes. No licensing, legislative or certification requirements apply to this unit at the time of publication.
Notes
Elements and Performance Criteria
1 Operate mobile crane
- 1.1 Job hazards are identified and required actions taken to minimise, control or eliminate identified hazards
- 1.2 Ascent and descent to and from crane is completed in accordance with relevant codes of practice and workplace procedures
- 1.3 Required signals are correctly given, interpreted and followed in accordance with appropriate workplace procedures
- 1.4 Boom is positioned to ensure load to be lifted is plumbed under hook
- 1.5 Load is hoisted and lowered into position using crane movements in accordance with appropriate workplace procedures
- 1.6 Crane controls are operated smoothly
- 1.7 Crane is shut down and secured during periods of non-operation in accordance with manufacturer specifications and workplace procedures
2 Monitor lift conditions
- 2.1 Load is constantly monitored to ensure load and structural stability
- 2.2 Conditions that may affect continuing stability of crane are identified and monitored
- 2.3 Unplanned situations are responded to in accordance with workplace procedures in a manner that minimises risk to personnel and equipment
- 2.4 Dogger is advised of new information that affects lift
- 2.5 Necessary changes to job plan are discussed and confirmed with rest of crew
- 2.6 Advice is sought from supervisor where there is doubt about correct response to unanticipated conditions or conflict with customer request
- 2.7 Supervisor and/or allocator is advised of concerns about completing job within timeframe
3 Implement shutdown procedures
- 3.1 Relevant motion locks and brakes are applied
- 3.2 Crane is shut down using correct sequence of procedures in accordance with manufacturer specifications and workplace procedures
- 3.3 Routine post-operational equipment checks are carried out in accordance with manufacturer specifications
4 Pack up crane
- 4.1 Crane is de-rigged with other crane personnel in accordance with manufacturer instructions
- 4.2 All lifting equipment and crane components are checked in consultation with crane personnel for signs of deterioration or damage in accordance with appropriate Australian Standard
- 4.3 Damaged or worn equipment is segregated and reported to authorised person for testing, repair and destruction (where appropriate)
- 4.4 Crane and equipment are correctly stowed and secured in accordance with manufacturer instructions and appropriate Australian Standard
5 Complete job records
- 5.1 Customer feedback is sought about satisfaction with completed job, and areas of concern are reported in accordance with workplace procedures
- 5.2 Customer signature on job completion documentation is obtained
- 5.3 Required workplace records are updated accurately and promptly, and processed in accordance with workplace procedures
No information
No information
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| D5086 | TLID3036A | Lift and move load using a mobile crane | Unit of competency |