Unit of competency Outline
Date retreived
22/07/2026 11:34 PM AWST
22/07/2026 11:34 PM AWST
Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Manage strategic contracts
Manage strategic contracts
Unit of competency
National Code
PSPPROC607A
PSPPROC607A
State Code
D3743
D3743
TGA Status
Replaced
Replaced
DTWD Status
Replaced
Replaced
State Implementation and Classification
Approved Date
05/11/2014
Field of Education
080301 - Business Management
Original Release Date
05/11/2014
Nominal Hours
50
Description
This unit covers the competencies required to manage contracts for strategic purchases, to effectively minimise risks and achieve value for money to meet an organisation's core objectives. It includes managing the establishment, performance and evaluation of strategic contracts.In practice, managing strategic contracts may occur in the context of other generalist and specialist work activities, such as maintaining and enhancing confidence in public service or local government, establishing and maintaining strategic networks, managing compliance with legislation in the public service or local government, managing risk, developing a business case, planning for strategic procurement, coordinating strategic procurement and negotiating strategic procurement.No licensing, legislative, regulatory or certification requirements apply to this unit at the time of endorsement.
Notes
Elements and Performance Criteria
1. Manage contract establishment
- 1.1. Requirements of contracts and strategic initiatives are discussed, clarified and agreed by all parties.
- 1.2. Responsibilities for establishing and carrying out procedures are assigned to achieve contract outcomes.
- 1.3. Effective communication strategies and processes are established and implemented to assist ongoing communication between internal and external stakeholders and contractors.
- 1.4. Relationship management is undertaken of all levels of personnel involved in procurement and contract management, within probity boundaries.
- 1.5. Strategic relationships are established and managed within probity boundaries to improve procurement capability and performance.
- 1.6. Risk management plans are updated according to organisational policy and procedures.
2. Manage contract performance
- 2.1. Progress of contracts is monitored against set targets and performance measures to ensure success of procurement activities.
- 2.2. Should monitoring find that set targets, performance measures and probity requirements are not being met, action is taken to rectify performance in a timely manner.
- 2.3. Advice and support are provided to solve problems, make improvements and maintain progress.
- 2.4. Disputes are managed promptly according to contractual conditions to achieve resolution and maintain contract performance and progress.
- 2.5. Opportunities to continuously improve procurement outcomes are sought and negotiated with contractors.
- 2.6. Approvals are provided or gained for contract variations that are negotiated and agreed between the parties.
- 2.7. Opportunities are provided for stakeholders and contractors to have input into and receive feedback on progress during the performance of the contract.
- 2.8. Internal and external stakeholders are engaged as necessary throughout the life of the contract to maintain progress.
3. Manage contract evaluation
- 3.1. Evaluation of contract performance is undertaken relative to planned performance measures and in consultation with stakeholders and contractors.
- 3.2. Where stakeholders and contractors do not agree, dispute resolution is undertaken according to organisational policy and procedures.
- 3.3. Conclusions are detailed against agreed criteria to provide a complete picture of performance of contractors, organisation's procurement processes and value for money.
- 3.4. Performance of strategic initiatives is measured relative to planned outcomes in consultation with industry and other stakeholders.
- 3.5. Lessons learnt from evaluations of contracts and strategic initiatives are documented according to organisational requirements and used to continuously improve future procurement activities.
- 3.6. Contractors and stakeholders are advised of evaluation outcomes in a timely manner according to organisational guidelines.
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Contracts and strategic initiatives may include:
non-traditional procurement and finance activities
strategic procurement activities, such as industry development
in-house option directives
inter and intra-government agreements
memoranda of understanding and memoranda of agreement
public private partnerships (PPP)
purchases from suppliers
coordinated procurement arrangements
whole of government procurement arrangements
cooperative procurement arrangements.
Stakeholders may include:
end users
customers or clients
sponsors
current or potential providers or suppliers
technical or functional experts or advisers
commonwealth, state or territory, and local government
the organisation
other public sector organisations
employees, unions and staff associations
industry bodies
local communities
lobby groups and special user groups.
Monitoring may involve:
progress meetings and regular progress reports from contractor
visits to contractor's premises
provision of samples
tests and verification
independent audit
end-user feedback.
Contract variation may include modification of:
targets
performance measures
procurement plans
resourcing
monitoring and evaluation processes.
Evaluation of contractor performance may include:
strengths and weaknesses
client acceptance of service delivery (client satisfaction)
meeting delivery and completion dates
compliance with other contractual requirements
performance in relation to relevant policy objectives, such as industry development, care for the environment, OHS and affirmative action
achievements of the contractor in developing Australian and New Zealand supply networks
general relationships, including effectiveness of communication at all levels
performance of key technical personnel
acceptability and cost of whole-of-life technical support, including lead times and availability of spares and maintenance services
achievements in innovation and quality improvement programs
acceptability and suitability for future agreements, including potential status as an approved contractor
adherence to codes of practice and codes of conduct.
Evaluation of organisation's procurement processes may focus on:
effectiveness of project management, including project plan and responsibilities and accountabilities set out in it
quality of the business case, as indicated by achievement of planned outcome and contribution to program objectives
effectiveness of contractor qualification processes
value obtained in bid clarification and post-tender negotiation
effectiveness of project management systems, focusing particularly on management information
effectiveness of risk management, including corruption risks and probity risks
methods for controlling variations in cost, time, quality and performance from initial planning to completion
adequacy of safeguards against fraud, error and impropriety
incidence of material losses due to waste or inefficiency
overall performance in terms of cost, time, service and quality
compliance with procurement policy.
Value for money must reflect:
whole-of-life program benefits
residual values
disposal costs or disposal return
costs of parts
servicing and maintenance
industry benchmarks.
Contracts and strategic initiatives may include:
non-traditional procurement and finance activities
strategic procurement activities, such as industry development
in-house option directives
inter and intra-government agreements
memoranda of understanding and memoranda of agreement
public private partnerships (PPP)
purchases from suppliers
coordinated procurement arrangements
whole of government procurement arrangements
cooperative procurement arrangements.
Stakeholders may include:
end users
customers or clients
sponsors
current or potential providers or suppliers
technical or functional experts or advisers
commonwealth, state or territory, and local government
the organisation
other public sector organisations
employees, unions and staff associations
industry bodies
local communities
lobby groups and special user groups.
Monitoring may involve:
progress meetings and regular progress reports from contractor
visits to contractor's premises
provision of samples
tests and verification
independent audit
end-user feedback.
Contract variation may include modification of:
targets
performance measures
procurement plans
resourcing
monitoring and evaluation processes.
Evaluation of contractor performance may include:
strengths and weaknesses
client acceptance of service delivery (client satisfaction)
meeting delivery and completion dates
compliance with other contractual requirements
performance in relation to relevant policy objectives, such as industry development, care for the environment, OHS and affirmative action
achievements of the contractor in developing Australian and New Zealand supply networks
general relationships, including effectiveness of communication at all levels
performance of key technical personnel
acceptability and cost of whole-of-life technical support, including lead times and availability of spares and maintenance services
achievements in innovation and quality improvement programs
acceptability and suitability for future agreements, including potential status as an approved contractor
adherence to codes of practice and codes of conduct.
Evaluation of organisation's procurement processes may focus on:
effectiveness of project management, including project plan and responsibilities and accountabilities set out in it
quality of the business case, as indicated by achievement of planned outcome and contribution to program objectives
effectiveness of contractor qualification processes
value obtained in bid clarification and post-tender negotiation
effectiveness of project management systems, focusing particularly on management information
effectiveness of risk management, including corruption risks and probity risks
methods for controlling variations in cost, time, quality and performance from initial planning to completion
adequacy of safeguards against fraud, error and impropriety
incidence of material losses due to waste or inefficiency
overall performance in terms of cost, time, service and quality
compliance with procurement policy.
Value for money must reflect:
whole-of-life program benefits
residual values
disposal costs or disposal return
costs of parts
servicing and maintenance
industry benchmarks.
The Evidence Guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment
Competency must be demonstrated in managing strategic contracts consistently and in accordance with legislative and organisational requirements.
Critical aspects for assessment and evidence required to demonstrate competency in this unit
Assessment must confirm the ability to:
develop contract management plans and sub-plans suited to the nature of the contracts
establish contract management relationships with stakeholders using strategic techniques such as start up workshops, service level agreements, etc.
implement contract management plans
manage contractors to ensure the delivery of contract outcomes, using flexibility and initiative to deal with issues as they arise
implement contract performance measures
provide contractors with performance feedback
deal promptly and proactively with contract disputes and refer to higher authority when this is not possible
communicate effectively with internal and external stakeholders about the operation of contracts
uphold probity standards in all dealings with contractors.
Consistency in performance
Competency should be demonstrated by providing evidence of undertaking a range of relevant work tasks in an actual or simulated procurement environment on at least two separate occasions.
Context of and specific resources for assessment
The unit of competency is to be assessed in the workplace or a simulated workplace environment.
Access may be required to:
legislation, policy, procedures and protocols relating to managing strategic contracts
codes of conduct and codes of practice
long-term government policy papers, such as White Papers
strategic procurement plans and direction statements
workplace scenarios and case studies relating to a range of strategic procurement and disposal activities.
Method of assessment
The following assessment methods are suggested:
questions to assess understanding of relevant legislation and procedures
review of strategies and approaches adopted for managing strategic contracts
review of contract management plans and related sub-plans, such as transition plans, probity plans, contract variations, contract performance reports and reviews, budgets, negotiation notes from meetings with contractors, risk assessments, formal sign-offs and approvals, contract closure reports, and other documentation prepared or reviewed by the candidate in a range of contexts
review of stakeholder engagement approaches adopted by the candidate.
In all cases, practical assessment should be supported by questions to assess underpinning knowledge and those aspects of competency which are difficult to assess directly. Candidates for this qualification must demonstrate a high level of understanding and practical workplace application of underpinning knowledge. Questioning techniques should suit the language and literacy levels of the candidate.
Guidance information for assessment
Evidence must be gathered over time in a range of contexts to ensure the person can achieve the unit outcome and apply the competency in different situations or environments.
Holistic assessment with other units relevant to the industry sector, workplace and job role is recommended, for example:
PSPETHC601B Maintain and enhance confidence in public service
PSPLEGN601B Manage compliance with legislation in the public sector
PSPMNGT607B Develop a business case
PSPMNGT608B Manage risk
PSPPM601B Direct complex project activities
PSPPROC604B Plan for strategic procurement
PSPPROC605B Coordinate strategic procurement
PSPPROC606B Negotiate strategic procurement.
Overview of assessment
Competency must be demonstrated in managing strategic contracts consistently and in accordance with legislative and organisational requirements.
Critical aspects for assessment and evidence required to demonstrate competency in this unit
Assessment must confirm the ability to:
develop contract management plans and sub-plans suited to the nature of the contracts
establish contract management relationships with stakeholders using strategic techniques such as start up workshops, service level agreements, etc.
implement contract management plans
manage contractors to ensure the delivery of contract outcomes, using flexibility and initiative to deal with issues as they arise
implement contract performance measures
provide contractors with performance feedback
deal promptly and proactively with contract disputes and refer to higher authority when this is not possible
communicate effectively with internal and external stakeholders about the operation of contracts
uphold probity standards in all dealings with contractors.
Consistency in performance
Competency should be demonstrated by providing evidence of undertaking a range of relevant work tasks in an actual or simulated procurement environment on at least two separate occasions.
Context of and specific resources for assessment
The unit of competency is to be assessed in the workplace or a simulated workplace environment.
Access may be required to:
legislation, policy, procedures and protocols relating to managing strategic contracts
codes of conduct and codes of practice
long-term government policy papers, such as White Papers
strategic procurement plans and direction statements
workplace scenarios and case studies relating to a range of strategic procurement and disposal activities.
Method of assessment
The following assessment methods are suggested:
questions to assess understanding of relevant legislation and procedures
review of strategies and approaches adopted for managing strategic contracts
review of contract management plans and related sub-plans, such as transition plans, probity plans, contract variations, contract performance reports and reviews, budgets, negotiation notes from meetings with contractors, risk assessments, formal sign-offs and approvals, contract closure reports, and other documentation prepared or reviewed by the candidate in a range of contexts
review of stakeholder engagement approaches adopted by the candidate.
In all cases, practical assessment should be supported by questions to assess underpinning knowledge and those aspects of competency which are difficult to assess directly. Candidates for this qualification must demonstrate a high level of understanding and practical workplace application of underpinning knowledge. Questioning techniques should suit the language and literacy levels of the candidate.
Guidance information for assessment
Evidence must be gathered over time in a range of contexts to ensure the person can achieve the unit outcome and apply the competency in different situations or environments.
Holistic assessment with other units relevant to the industry sector, workplace and job role is recommended, for example:
PSPETHC601B Maintain and enhance confidence in public service
PSPLEGN601B Manage compliance with legislation in the public sector
PSPMNGT607B Develop a business case
PSPMNGT608B Manage risk
PSPPM601B Direct complex project activities
PSPPROC604B Plan for strategic procurement
PSPPROC605B Coordinate strategic procurement
PSPPROC606B Negotiate strategic procurement.
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| C8259 | PSPPROC602B | Direct the management of contracts | Unit of competency |
Replaced By
| State Code | National Code | Title | Type |
|---|---|---|---|
| AWU24 | PSPPCM023 | Manage strategic contracts | Unit of competency |